The M7 pylon of the bridge on island Russian

Kuznetsk metal constructions had a control Assembly of cable core nodes of M7 pylon of the bridge on island Russian Kuznetsk metal constructions has successfully conducted a test Assembly of the twelve nodes of the cable core pylon M7 bridge across the Eastern Bosphorus Strait. Test Assembly were representatives of the Customer JSC "IC BRIDGE". According to the chief plant engineer Evgeny Morozov: "It was a serious examination of our factory, we have successfully passed" The core design consists of two beams with formwork pipes through which are passed through the shrouds. The total weight of the block core of the pylon was 111 tons.